The CREATE partners completed a combined Final Environmental Impact Statement (EIS) and Record of Decision (ROD) for the 75th St. CIP in 2014.
Funding has been secured for the 75th St. CIP final design and partial construction.
Design of the Forest Hill Flyover (P3) and 71st St. Grade Separation (GS19) projects began in 2019 and was completed in 2022.
Design of viaduct and community mobility improvements associated with the 75th St. CIP began in 2019.
Temporary construction related to the Forest Hill Flyover (P3) began in 2020.
Design of the Rock Island Connection (P2) and Belt Junction and 80th St. Junction Replacements (EW2) projects began in 2020 and is anticipated to be completed in 2025.
Construction of the Forest Hill Flyover (P3) and 71st St. Grade Separation (GS19) began in October 2022 and is planned to conclude by the end of 2025.
In 2022, in association with the Forest Hill Flyover (P3) and 71st St. Grade Separation (GS19) projects, construction was completed for ninety-one community mobility improvement projects. In conjunction with these efforts, four viaducts are being designed and constructed.
The schedule for construction of the Rock Island Connection (P2) and Belt Junction and 80th Street Junction Replacements (EW2) will be determined once funding is secured.
Public involvement is occurring throughout the design and construction process.